How councils advertise development applications, and the BA20 and BA20A notices you give before work that affects a neighbour’s land.
Quick answer: in WA the council advertises development applications. Complex applications go to owners and occupiers within 200 m for 28 days with a sign on the site. Other advertised applications run for 14 days, and council can ask you to pay the costs and put up the signs. Before building or demolition work that affects a neighbour’s land, you give a BA20 or BA20A notice and need their consent or a court order.
Working out dates? The notice period calculator counts the days for you, including business days and holidays.
Free template: BA20 cover letter (WA), ready to copy and print.
| Who notifies | The local government. It can make the applicant pay the advertising costs and put up the signs |
|---|---|
| Complex applications | Owners and occupiers of every property within 200 m, plus others likely to be affected, and a sign on the land. 28 days |
| Other advertised applications | Owners and occupiers council thinks are likely to be affected, a newspaper notice or a sign, as council decides. 14 days |
| When it is required | Always for complex applications. For others when the use is class A, the plans do not comply with the scheme, a heritage assessment is needed, or the scheme says so |
We checked the regulations as at 1 May 2024. Check for later changes with your council.
Source: Planning and Development (Local Planning Schemes) Regulations 2015, Schedule 2 cl 64 and 64A (as at 01 May 2024, legislation.wa.gov.au). Checked 7 October 2026.
Under Part 6 of the Building Act 2011, the person responsible for the work (builder, demolition contractor or owner) needs each affected owner’s consent, or a Magistrates Court order, before work that:
The owner has 28 days to consider the notice, or 14 days after any further information you give them. Some fence removals need only 7 business days notice.
Source: Form BA20 Notice and request for consent to encroach or adversely affect (Building and Energy, wa.gov.au). Checked 7 October 2026.
Source: Form BA20A Notice and request for consent: protection structures, party walls, removal of fences, access to land (wa.gov.au). Checked 7 October 2026.
Source: City of Perth: Work Affecting Other Land. Checked 7 October 2026.
Use our construction notice template for the wording, and keep the dated list of addresses you delivered to. If anyone later says they were not told, that list is your answer.
What each council publishes about advertising.
| Who notifies | The City sends letters. You provide and put up signs for complex applications |
|---|---|
| Who is told | Standard: adjoining owners and occupiers. Complex: everyone within 200 m |
| How long | Standard: 14 days. Complex: 28 days |
No sign for standard applications. Complex applications need a sign at least 1.0 m by 1.5 m on each street boundary.
Source: City of Stirling Local Planning Policy 6.18 Public Consultation. Checked 7 October 2026.
| Who notifies | The City |
|---|---|
| Who is told | Potentially affected parties |
| How long | As set by the regulations |
For work affecting other land, the City points to the BA20 and BA20A forms and the 28 day consent period.
Source: City of Perth: Advertised planning applications. Checked 7 October 2026.