How to notify neighbours in South Australia

Notified development under the Planning, Development and Infrastructure Act, the sign you have to put up, and the notice you give before work that affects the land next door.

Street map with a dashed 20 metre circle around a pinned site and notices going to every home inside it

Quick answer: for a notified performance assessed development, the council or other relevant authority writes to owners and occupiers within 60 metres, but you put up the sign on the site (or pay the authority to do it). People have 15 business days to comment. Separately, building work that could affect the stability of a neighbour’s land needs a notice served at least 20 business days before work starts.

Notified development applications

Who notifiesThe relevant authority (usually council) writes to neighbours. The applicant puts up the site notice, or pays the authority to
Who is toldOwners and occupiers of land within 60 metres, by letter or registered email. The public through the site sign
How long15 business days. Posted notices are taken to arrive after 4 business days
The signAt least A3, weatherproof, between 600 mm and 1.5 m above the ground. Photograph it within 1 business day of putting it up and again within 2 business days after the period ends

This applies to performance assessed applications that need notification under the Planning and Design Code. Neighbours who comment may be invited to speak at the assessment panel.

Source: PlanSA: Performance assessed developments (including outline consent applications) that require notification. Checked 7 October 2026.

Source: Practice Direction 3: Notification of performance assessed development applications. Checked 7 October 2026.

Building work that affects the land next door

  • If your work could affect the stability of a neighbour’s land, serve a Form 1 notice on the owner at least 20 business days before work starts (PDI Act s 139).
  • A party wall needs notice and the adjoining owner’s written consent (ss 147 and 148).
  • If you need access to the neighbour’s land, they have 10 business days to respond. If they refuse, you can apply to the Environment, Resources and Development Court.

Source: Law Handbook (Legal Services Commission of SA): Building work affecting other land. Checked 7 October 2026.

Beyond the people within 60 metres

Use our construction notice template for the wording, and keep the dated list of addresses you delivered to. If anyone later says they were not told, that list is your answer.

Council by council

What each council publishes about notified applications.

City of Adelaide

Who notifiesCouncil, by letter to registered owners and occupiers. You put up the sign or pay council to
Who is toldOwners and occupiers within 60 metres
How long15 business days

Council lists a sign fee and a notification fee on its page. Check the current amounts with council.

Source: City of Adelaide: Public notification. Checked 7 October 2026.

City of Onkaparinga

Who notifiesThe relevant authority
Who is toldNeighbours and other interested parties
How long15 business days

Development not listed in Table 5 of the zone in the Planning and Design Code triggers notification. Comments go through the PlanSA portal.

Source: City of Onkaparinga: Applications on Public Notification. Checked 7 October 2026.