Notice templates · NT builders and owners

Protection works notice to adjoining owner (NT): free template

Excavation or demolition close to the building next door means the adjoining owner hears from you before work starts.

An excavator digging beside a neighbour's house in warm afternoon light while a worker hands the neighbour a letter

Quick answer: In the Northern Territory, where excavation or demolition is close to an existing building, the owner must protect the adjoining property. Before work starts, notify the adjoining owner with the building work, the protection works and the certifier’s details. They have 14 days to respond, and no response counts as agreement. Disagreements go to the Director of Building Control.

When to send it

Send it once your certifier has signed off the protection works design, and at least 14 days before the work starts. Allow longer if you are posting it.

The rules behind it

The rules are in Part 9 of the Building Act 1993 and regulation 22 of the Building Regulations. Your certifier can confirm what to attach. More on the Northern Territory notification rules page.

The template

Change everything in [square brackets], delete anything that does not apply and check it against your own conditions before you print.

[Your business name or your name]
[Licence number if a builder] · [Phone] · [Email]

[Date]

To [adjoining owner’s name], owner of [neighbour’s address]

Notice of protection works: [site address]

We are planning [excavation / demolition] at [site address], close to your building. Before work starts, we want you to know what is planned and how your property will be protected.

The building work
[Short description, eg demolition of the existing house and excavation for a new slab, about [x] metres from your house.]

The protection works
[Eg temporary shoring along the boundary, a dilapidation survey of your building before work starts, and vibration monitoring during demolition.] Details are enclosed.

Building certifier
[Name], [registration number], [phone or email].

Timing
Work is planned to start on [date] and the protection works will be in place before then.

Your response
You have 14 days from receiving this notice to respond. If we do not hear from you, it is taken as agreement. If you disagree, the matter can go to the Director of Building Control.

Please call me on [mobile] if you would like to meet on site or have your own engineer look at the plans.

Kind regards,
[Name]
[Business name, or owner of [site address]]

Tips that save complaints later

  • Photograph the neighbour’s walls and paths before work starts and offer them a copy.
  • In the build-up season, plan for storms. Say what happens to an open excavation in heavy rain.
  • Keep a note of when the notice was delivered so you know when the 14 days end.